Skip to content

Folk stories and other urban myths

Michael Chesterman
Michael Chesterman October 9, 2017
SHARE

Over the course of the recent security of payment (SOP) debate that has culminated in the tabling of the Building Industry Fairness (Security of Payment) Bill 2017 (BIF Bill), I have noted several significant misconceptions about the 2014 amendments to BCIPA.

These misconceptions are:

MISCONCEPTION ONE

In 2014 respondents, for the first time, were afforded an opportunity to provide a ‘2nd chance’ payment schedule before claimants could proceed to adjudication.

This is not the case.

From the date BCIPA was assented to on 20 May 2004, under section 21(2) a respondent had the opportunity to provide a ‘2nd chance’ payment schedule if the claimant decided to go to adjudication.

Why are respondents afforded a ‘2nd chance’ to provide a payment schedule?

Because the short time (5 days) given to a respondent to serve a ‘2nd chance payment schedule’ provides the parties with a last opening to settle a matter.

FACT 1: A second opportunity to give a payment schedule before proceeding to adjudication has always existed under BCIPA.

MISCONCEPTION TWO

The 2014 changes made it so that it was no longer an offence if a respondent failed to provide a payment schedule.

This is not the case.

Unfortunately, this misconception was recently affirmed by a departmental officer in a public hearing into the BIF Bill on 20 September 2017.

The following is an exchange that took place during the public hearing:

Department: Yes. The one issue that has been raised a lot today was the removal of a penalty for the non-provision of a payment schedule after a payment claim. That is what has been raised today. Would you like a more detailed analysis?

Committee: Nothing too lengthy. I was not in parliament at that stage. Was it an amendment or a change of regulation?

Department: That was an amending bill that affected those changes.

Committee: Thank you. That is still in effect, clearly, until this passes

Why does this misconception matter? Surely this is a trivial issue I can hear some say.

It matters because this misconception has developed like a folk story and is rolled out to justify the exclusive focus on subcontractors in the BIF Bill. An analysis of these amendments should be factually based and the right solutions for subcontractors and builders should be well thought out.

The situation from the date BCIPA was assented to in 2004 is that the failure to provide a payment schedule by a respondent has never been an offence.

Section 18 of the BCIPA has always stated the following:

“A respondent served with a payment claim may reply to the claim by serving a payment schedule on the claimant”

Why has this been the situation since 2004?

  • Because it was considered not necessary to compel a respondent, who received a BCIPA endorsed payment claim and intended to fully pay the claimant, to respond with a payment schedule.
  • Because if a respondent fails to serve a payment schedule for any reason, and they fail to pay the claimed amount by the due date, then they can only raise jurisdiction grounds in any adjudication response to an adjudication application lodged by a claimant. This was considered sufficient penalty for a respondent not serving a payment schedule and then failing to pay the claimed amount by the due date.

However, it is certainly the case that the BIF Bill now compels respondents to provide a payment schedule in all cases, and creates an offence should a respondent fail to do so.

The BIF Bill explanatory notes, clause 76 states:

“Clause 76 incorporates and varies section 18 of the repealed BCIPA. It provides that a respondent given with a payment claim must serve a payment schedule to the claimant, (whether or not the respondent intends to pay the amount stated in the payment claim), unless they have a reasonable excuse. The clause also sets out the timeframes for serving a payment schedule. Failure to provide a payment schedule is an offence, with a maximum penalty of 100 penalty units. The offence reflects the importance of open communication and providing certainty to claimants about whether a respondent intends to pay. The opportunity to proceed to judgment or adjudication will also arise sooner.”

FACT 2: There has never before BIF been a penalty for the failure to provide a payment schedule.

MISCONCEPTION THREE

After 2014 in all circumstances respondents were afforded the opportunity to include new reasons in an adjudication response that they did not outline in the payment schedule.

This is not the case.

It is true that in respect of ‘complex claims’ (payment claim > $750,000), respondents were granted the opportunity to include new reasons in an adjudication response.

Why?

The explanatory notes to BCIPA 2014 state:

“Under the Bill, for complex claims, the respondent will be able to include in its adjudication response all relevant reasons for withholding payment, whether or not these matters were raised in the payment schedule. This will allow the adjudicator to fully consider the information relevant to the payment claim. However, if additional reasons for withholding payment are included in the payment schedule this can be taken into account by the adjudicator when apportioning the fees of the adjudication.”

In respect to ‘standard claims’, the situation always remained as it has been since 2004, namely the respondent is prevented from introducing any reasons in their adjudication response that they did not outline in the payment schedule.

For the 2016/17 financial year, of the 614 adjudication applications lodged with the QBCC, 598 were of a standard claim category. Unless your claim was more than ¾ of a million dollars this change had no impact.

In my view, the reasoning being expressed that the 2014 amendments went too far and need an extreme rollback does not add up in this instance. Again, I would stress that the significance of this is to ensure that the positions being advocated are based on facts, not misconceptions.

FACT 3: The change to allow new reasons applied to only 4% of all adjudications since 2014.

In summary, there are some good improvements on the 2004 and 2014 version of BCIPA in the new BIF Bill but there are also too many misconceptions that have spread through the industry like folktales passed down from one person to the other without reference to the actual history. No one questions the need for improvement but let’s start with the facts and the right questions.

If you would like to know more about the operation of BCIPA then please feel free to contact Michael Chesterman at michael@helix.legal or Earl Tan at earl@helix.legal

Not intended as legal advice. Read full disclaimer.
Michael Chesterman
Michael Chesterman October 9, 2017

The insight you need, right in your inbox.

Stay up to date with all the important updates - legal and otherwise - plus get exclusive invites to events designed to educate and empower our industry.